项目团队已完成项目管理计划中的所有可交付成果。该团队期待尽快做出收尾决定。但是,项目经理正在努力向相关方证明该决定的合理性。 若要避免这个问题,项目经理应该事先做什么?The project team has completed all the deliverables in the project management plan.The team is expecting a closure decision to be made soon. However,the project manager is struggling to justify the decision with the stakeholders. What should the project manager have done to avoid this issue?

发布于 2021-04-19 22:42:49
【单选题】
A 定义项目可交付成果的验收标准 Defined the project deliverable's acceptance criteria。
B 确认满足发起人的期望 Verified that the sponsor's expectations were met。
C 在进入最终产品阶段之前解决所有客户投诉 Addressed all customer complaints before going into the final product phase.
D 确保最终产品符合承诺的业务价值 Ensure that the end product complied with the committed business value.

查看更多

关注者
0
被浏览
133
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题

手机
浏览

扫码手机浏览

分享
好友

在线
客服