项目经理正在领导一个涉及跨职能需求和变更的新项目,一些关键相关方正在抵制这些变更,项目经理应该做什么?A project manager is leading a new project that involved cross-functionalrequirements and changes.Some key stakeholders are resisting the changes.What should the project manager do?
发布于 2021-04-19 22:42:04
【单选题】 A 收集相关方需求 Gather stakeholder requirements. B 请项目管理办公室(PMO)协助 Ask the project management office(PMO) for assistance. C 举行引导式研讨会 Conduct a facilitation workshop. D 计划团队建设练习 Plan a team-building exercise.