【单选题】
A 通知变更控制委员会(CCB),并修改项目参数 Inform the change control board(CCB),and revise project parameters.
B 更新风险登记册,并制定应对措施 Updated the risk register,and develop a response.
C 执行风险分析,并在成本基准中添加应急储备 Perform a risk ana-lysis,and add a contingency reserve to the cost baseline.
D 致电政府联系人以获取更多信息 Call government contacts to obtain more information.