随着项目进展,项目经理预测到即将开展的活动中存在一些风险。项目经理应该使用哪一份文件进行风险分类?As the project progresses, the project manager predicts that there are certain risks in the upcoming activities. Which document should the project manager use for risk classification?
发布于 2021-04-19 22:42:55
【单选题】 A 风险分解结构 Risk Breakdown Structure B 风险管理计划 Risk Control Plan C 风险登记册 Risk Register D 风险绩效报告 Risk Performance Report