在执行阶段,客户告诉项目经理,三个现有工具的软件版本已更改。现在,三个接口必须以不同方式实施。 项目经理应该怎么做?In the implementation phase, the customer tells the project manager that the software versions of three existing tools have changed. Now the three interfaces must be implemented in different ways. What should the project manager do?
发布于 2021-04-19 22:43:18
【单选题】 A 更新工作分解结构(WBS) To update the Work Breakdown Structure (WBS) B 更新风险登记册 To update the Risk Register C 开始变更管理过程 To start the change control process D 审查项目管理计划 To review the project management plan