Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.

发布于 2021-04-24 03:35:36
【多选题】
A Carry out a lot-size calculation for every material with net requirements
B Perform backward scheduling to determine the availability dates of purchase requisitions.
C Carry out a net requirement calculation for every material included in the planning run.
D F lag materials that have been subject to an activity relevant to MRP.