项目经理正在谋求与关键相关方一起验证某项目是否符合公司战略,但其中的几位相关方却一再拒绝开会请求。项目经理接下来应该如何进行该验证工作?The project manager is seeking to verify with key stakeholders whether a project meets the company's strategy. However, several of the parties involved have repeatedly refused to meet requests. How should the project manager carry out the verification work next?

发布于 2021-04-24 23:10:26
【单选题】
A 将该问题上报给项目发起人,说明某些相关方在忽视开会请求 Report the issue to the project sponsor, indicating that some parties are ignoring the meeting request
B 通过电子邮件或电话单独与未参会的相关方开展项目验证工作 Verify the project with the non-participating parties individually by email or phone
C 更新风险登记册,将未参与该验证工作的相关方的姓名记入其中 Update the risk register to include the names of interested parties not involved in the verification exercise
D 仅与参会的相关方举行验证会议 Validation meetings will be held only with participating parties

查看更多

关注者
0
被浏览
92
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题

手机
浏览

扫码手机浏览

分享
好友

在线
客服