一个施工项目的已批准成本基准包含一些已识别风险的储备。在执行阶段,发生了一次地震,但该项目并未考虑此风险,需要资金进行灾后恢复。项目经理应该做什么?The approval cost baseline for a construction project includes some identified risk reserves. During the implementation phase, an earthquake occurred, but the project did not consider this risk and required funding for post-disaster recovery.What should the project manager do?

发布于 2021-04-24 18:10:51
【单选题】
A 无需寻求授权即可变更项目的成本基准,并继续进行项目工作 No need to seek authorization to change the cost basis of the project and continue the project work
B 向变更控制委员会(CCB)提交申请,以获得额外资金和成本基准变更 Submit an application to the Change Control Board (CCB) for additional funding and cost baseline changes
C 在未咨询CCB的情况下,使用已识别风险的储备来支付灾后恢复成本 Use of identified risk reserves to pay for disaster recovery costs without consulting CCB
D 要求管理层授权将已识别风险的储备用于支付灾后恢复成本 Require management to authorize the use of identified risk reserves for post-disaster recovery costs