根据沟通管理计划,项目应该使用仪表板向相关方传达信息。一些团队成员在更新他们在仪表板上的项目数据时遇到了一些困难。对项目经理来说,最好的行动方案是什么?According to the communications management plan, the project should use a dashboard to communicate information to stakeholders. Some team members are struggling to keep their project data current. What is the best action for the project manager?

发布于 2021-04-24 18:10:28
【单选题】
A 鼓励团队成员尽可能输入任何信息 Encourage team members to enter any information whenever they can
B 向那些在及时报告上有困难的团队成员提供帮助 Offer help to those team members who are struggling to report on time
C 让团队专注于他们的工作并代表他们报告状态 Have the team focus on their work and report the status on their behalf
D 减少或调整那些无法保持数据最新状态的格式 Reduce or adjust the format of those not able to keep their data current