项目经理通知敏捷团队成员,由于意外的个人问题,产品负责人将不能参加即将到来的冲刺审查。这种情况下最可能的结果是什么?A project manager informs the agile team members that, due to unexpected personal issues, the product owner will be unable to attend the upcoming sprint review. What would be the most likely outcome of this situation?

发布于 2021-04-24 18:10:43
【单选题】
A 不清楚团队在冲刺期间开发的产品增量是否被接受 It will be unclear whether the product increment developed by the team during the sprint is accepted or not
B 团队无法确定他们用于开发产品的过程是否需要改进 The team will be unable to determine if the process they used to develop the product needs improvement
C 不会产生任何严重后果,因为产品负责人缺席了一次冲刺审查会议 There will be no significant consequences as a result of the product owner missing one sprint review meeting
D 无法确定项目团队在最新冲刺期间增加了多少价值 It will be impossible to determine how much value has been added by the project team during the latest sprint