由于没有空,具有批准权限的相关方拒绝了参与项目开工会议的邀请。该项目时间紧迫,及时开工对于满足截止日期至关重要。项目经理应该做什么?Due to the lack of time, interested parties with approval authority rejected the invitation to participate in the kick-off meeting. The project is urgent, and timely start-up is essential to meet the deadline. What should the project manager do?

发布于 2021-04-24 18:11:09
【单选题】
A 升级上报给项目发起人 The upgrade is reported to the project sponsor
B 在没有他们参加的情况下举行项目开工会议 Hold project kick-off meeting without their participation
C 将会议重新安排在他们能够参与的时间 Reschedule the meeting at a time when they can participate
D 询问与会者以确定开工会议是否有必要 Ask participants to determine if a kick-off meeting is necessary