【单选题】
A 将对该需求的潜在变更增加到项目章程中,然后立即调整项目成本和进度计划文件Addpotentialchangestotherequirementtotheprojectcharter,andthenimmediatelyadjusttheprojectcostandscheduledocumentation
B 对风险登记册不作修改,但就对项目成本和进度计划的影响征得项目发起人批准Therearenochangestotheriskregister,buttheimpactonprojectcostandscheduleisapprovedbytheprojectsponsor
C 分配必要人员应对该潜在变更,尽管该应对措施未在风险应对计划中获批Assignthenecessarypersonneltorespondtothispotentialchange,althoughtheresponsewasnotapprovedintheriskresponseplan
D 提出针对潜在变更的变更请求,并征得变更控制委员会(CCB)批准MakeachangerequestforapotentialchangeandobtainapprovalfromtheChangeControlBoard(CCB)