【单选题】
A 在风险登记册中关闭该风险,但要将相关的应急储备作为未来风险的缓冲Closerisksintheriskregister,butusetherelevantcontingencyreservesasabufferagainstfuturerisks
B 继续监督该风险,直到项目完成,因为未来还可能会发生该风险Continuetomonitortheriskuntiltheprojectiscompleted,astheriskmayoccurinthefuture
C 利用相关的风险储备分配额外资源,从而加速项目的推进Useassociatedriskreservestoallocateadditionalresourcestoaccelerateprojectschedule
D 在风险登记册中将该风险标记为已关闭,并减少相关的应急储备Marktheriskasclosedintheriskregisterandreducetherelevantcontingencyreserves