在冲刺评审中,团队只能提交已完成的工作,即满足商定的已完成的定义的工作。 谁负责确定工作是否完成?At the sprint review, the team is allowed to present only completed work—work that meets the agreed-upon definition of done. Who is responsible for determining if the work is done or not?
发布于 2021-04-19 22:42:10
【单选题】 A 客户 The customer B Scrum 主管 The scrum master C 产品负责人 he product owner D 开发团队 The development team