一位关键相关方没有空批准项目定义。项目经理下一步应该怎么做?A key stakeholder is unavailable to approve for a project definition. What should the project manager do next?
发布于 2021-04-19 22:42:41
【单选题】 A 跟进该相关方以获得批准 Follow up with stakeholder to obtain approval B 审查相关方参与计划 Review the stakeholder engagement plan C 暂停所有项目活动 Put all project activities on hold D 更新批准过程以删除此相关方的要求 Update the approval process to remove this stakeholder requirement