在定义活动过程中,一团队成员开始讨论一个项目经理从来没有听过的活动。此时项目经理应该怎么做?During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do?

发布于 2021-04-24 18:11:01
【单选题】
A 确保团队成员理解并将这些活动包含在活动清单里了 Make sure he has a good understanding of the activities and include the activities in the activity list
B 询问团队成员需要完成这些活动的原因 Ask the team member to explain why such an activity would be needed to complete the work package
C 确认所有团队成员都认同这些活动 Make sure the entire team agrees that the activities should be done
D 评估变更的影响 Evaluate the impact of the change

查看更多

关注者
0
被浏览
178
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题

手机
浏览

扫码手机浏览

分享
好友

在线
客服