一个大型项目涉及许多专业团队,在规划期间,项目经理需要团队负责人提供工作量估算以及与任务相关的最终成本。项目经理应该要求团队负责人提供什么?A large project involves many professional teams, and during planning, the project manager needs the team leader to provide workload estimates and the final costs associated with the task.What should the project manager ask the team leader to provide?

发布于 2021-04-24 18:10:33
【单选题】
A 单点估算,因为它们更准确并且更容易规划预算 Single-point estimates because they are more accurate and easier to plan your budget
B 对没有发生风险的任务进行一次估算,对与潜在风险相关的额外成本进行一次估算 Settle once for tasks where no risk has occurred, and estimate the additional costs associated with potential risks
C 基于最佳案例场景分析的单点估算 Single point estimation based on best case scenario ana-lysis
D 估算除风险经理处理之外的风险 Estimating risks other than those handled by the risk manager