一个使用多个供应商的项目估计将在两年内完成。在第一年结束时,发现存在重大预算超支。项目经理意识到必须将项目重新拉回控制,因此签发一项变更请求。若要支持这项变更请求,项目经理应该做什么?A project that uses several vendors is estimated to complete in two years.At the end of the first year,a significant budget overrun is identified that project must be brought back under control,the project manager issues change request.What should the project manager do to support the change request?
发布于 2021-04-24 18:11:14
【单选题】 A 更新变更控制过程 Update the change control progresses B 完成质量审计 Complete a quality audit C 召开风险研讨会 Conduct a risk workshop D 执行根本原因分析 Perform a root cause ana-lysis