在敏捷迭代中,由于意外的挑战,任务1无法按时完成。项目中的另一个团队依赖于任务1的及时完成以完成他们的项目部分。项目经理应该如何解决这个问题?During an agile iteration, Task 1 cannot be completed on time due to unexpected challenges. Another team within the project is depending on timely completion of Task 1 in order to fulfill their part of the project. How should the Project Manager resolve this issue?

发布于 2021-04-24 18:11:07
【单选题】
A 分别与两个团队会面,让他们想出一个方法来满足要求的最后期限并按时完成项目 Meet with both teams separately and ask them to figure out a way to meet the required deadlines and complete the project on time
B 与产品负责人会面,重新确定迭代待办事项列表的优先级,以免影响其他团队或义务 Meet with the product owner to reprioritize the iteration backlog so that it does not impact other teams or obligations
C 增加项目团队的成员数量,并增加迭代长度,以确保工作将按照进度计划完成 Increase the number of team members for the project team and increase the iteration length ensuring that the work will be completed according to schedule
D 让团队成员知道你希望他们在困难条件下尽最大努力,并确保在经验教训中注意迭代的挑战 Let team members know you want them to do their best under difficult circumstances, and make sure to note the iteration's challenges in lessons learned