Threemembersofyourprojectteamwanttopadtheirestimatesbecausetheybelievetherearecertainrisksthatmightmaterialize.WhatistheBESTwaytohandlethissituation?

发布于 2022-06-09 21:24:11
【单选题】
A Estimate the activities honestly, and then use a contingency reserve to cover any unexpected costs
B Allow more time for the work by adding a buffer to every activity in the schedule
C Tell the team members not to worry about it, and if the schedule is wrong it’s okay for the project to be late
D Crash the schedule