在某产品最终版本获批之前举行的相关方会议上,其中一位相关方抱怨称,该产品缺失一项重要功能。项目经理应先采取哪项措施?At a meeting of interested parties held before the final version of a product was approved, one of them complained that an important feature was missing. Which action should the project manager take first?

发布于 2021-04-24 23:09:23
【单选题】
A 讨论该问题,并让该相关方相信增加更多功能为时已晚 Discuss the issue and convince the stakeholders that it's too late to add more features
B 估算增加该功能的成本并让相关方予以批准 Estimate the cost of adding the functionality and get approval from relevant parties
C 利用定义的验收标准核实该功能是否属于项目范围 Verify that the function is within the scope of the project using the defined acceptance criteria
D 根据该相关方的要求提交变更请求 Submit a change request as required by the relevant party