某供应商联系项目经理,解释说由于台风破坏了他们的制造工厂,他们无法交付一个至关重要的项目组件,合同涉及保密条款和不可抗力条款。项目经理该做什么?A supplier contacted the project manager to explain that they were unable to deliver a vital component of the project due to typhoon damage to their manufacturing plant and that the contract involved confidentiality and force majeure clauses. What should a project manager do?
发布于 2021-04-24 23:09:28
【单选题】 A 启动索赔调查 Initiate a claim investigation B 修订风险管理计划 Revise the risk management plan C 根据合同处罚供应商 Punish the supplier according to the contract D 根据合同避免处罚供应商 Avoid punishing suppliers according to the contract