在一个住房项目中,房地产开发商和建筑承包商对由建筑承包商完成的工作质量意见不一致。房地产开发商拒绝支付已经完成的工作,并且还要求折扣。项目经理应该如何解决这个问题?In a housing project, real estate developers and contractors still disagree about the quality of work done by construction contractors. Property developers are refusing to pay for work that has already been done and are demanding discounts. How should the project manager solve this problem?

发布于 2021-04-24 23:10:17
【单选题】
A 聘请第三方来检查所完成的工作并确定应该提供的折扣 Hire a third party to review the work done and determine what discounts should be offered
B 建议改善住房项目,以补偿房地产开发商的期望 Proposed improvements to housing projects to compensate for the expectations of property developers
C 让房地产开发商计算折扣价格作为所谓不良工作质量的处罚。 Let property developers calculate discount prices as punishment for the alleged poor quality of work.
D 鼓励双方使用合同协议中规定的其他争议解决程序 The parties are encouraged to use other dispute resolution procedures set forth in the contractual agreement