项目经理将项目章程草案提交给运营经理,运营经理就该项目对团队的影响表达了顾虑,并将所顾虑之事上报给项目发起人。项目经理应更新哪个文件来定义与该投诉相关的活动?The project manager submits the draft project charter to the operations manager, who expresses concerns about the project's impact on the team and reports those concerns to the project sponsor. Which document should the project manager update to define the activities related to the complaint?
发布于 2021-04-24 23:10:15
【单选题】 A 效益管理计划 Benefit Management plan B 资源管理计划 Resource management plan C 相关方参与计划 Stakeholders participate in the plan D 沟通管理计划 Communication management Plan