【单选题】
A 通知发起人并请求修改结束日期以适应所提出的进度计划 Notify the originator and request modification of the end date to accommodate the proposed schedule
B 向相关方提醒项目制约因素并请求修改他们的意见 Remind stakeholders of project constraints and request modification of their comments
C 确定一个可以保证项目在结束日期之前完成的新关键路径 Identify a new critical path that will ensure that the project is completed before the end date
D 对项目管理计划进行赶工,以减少对所提出的进度计划进行延期 Work on the project management plan to reduce the delay to the proposed schedule