你向项目出资人提供了项目的成本估算,他对估算不满意,因为他认为价格太高了。他要你削减项目估算的15%,你该怎么做?You provide a project cost estimate to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do?

发布于 2021-04-24 18:11:16
【单选题】
A 启动该项目,并不断的节约成本 Start the project and constantly look for cost savings
B 告诉所有团队成员削减其估算的15% Tell all the team members to cut 15 percent from their estimates
C 告诉出资人要削减的活动 Inform the sponsor of the activities to be cut
D 加入工资率低的额外资源 Add additional resources with low hourly rates

查看更多

关注者
0
被浏览
108
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题

手机
浏览

扫码手机浏览

分享
好友

在线
客服