一个大型复杂项目的项目经理了解到,一位关键相关方反对在项目后期批准的变更,项目经理不愿冒犯这位相关方,但也不希望延迟该项目。项目经理应该做什么?The project manager of a large and complex project learned that a key party was opposed to changes approved later in the project, and the project manager was unwilling to offend the party, but did not mean to delay the project.What should the project manager do?

发布于 2021-04-24 18:11:17
【单选题】
A 与该相关方一起审查沟通管理计划 Review the communication management plan with the interested party
B 取消已批准的变更,以满足相关方的要求 Cancel approved changes to meet the requirements of interested parties
C 让相关方参考变更日志,以显示变更批准 Have interested parties refer to the change log to show change approval
D 与相关方一起讨论相关方参与计划 Discuss the stakeholder participation plan with the stakeholder