【单选题】
A 团队和相关方应该经常审查产品增量 The team and stakeholders should frequently review product increments.
B 项目相关方应该在每次冲刺中执行基于风险的刺探 The project stakeholders should conduct risk-based spikes in each sprint.
C 产品负责人和发起人应该对高风险的用户故事进行优先级排序 The product owner and the sponsor should prioritize high-risk user stories.
D 团队应该与Scrum主管一起实现结对编程 The team should implement pair programming with the scrum master.