承包商正在根据固定总价(FFP)合同执行一个翻新项目。在项目期间,承包商进行了多项仍在项目范围内的小变更,此外,一些相关方要求进行变更。项目经理应该怎么做?A contractor is performing a renovation project based on a firm fixed price (FFP) contract. During the project, the contractor makes multiple small changes that are still within the project’s scope In addition, several stakeholders request more changes. What should the project manager do?
发布于 2021-04-19 22:41:33
【单选题】 A 修改合同以纳入这些变更 Amend the contract to incorporate the changes B 将这些超范围变更添加到变更日志 Add the scope changes to the change log C 查阅沟通管理计划 Refer the communication management plan D 查阅变更管理计划 Consult the change management plan