项目经理向指导委员会展示项目章程,指导委员会非常担心预先分配的资源,因为相关方不了解他们在项目中的参与情况。若要避免这个问题,项目经理应该事先做什么?A project manager presents the project charter to the steering committee.The steering committee is concerned about preassigned resource allocation because the stakeholders are unaware of their participation in the project. What should the project manager have done to avoid this?
发布于 2021-04-19 22:42:55
【单选题】 A 获得相关方的期望 Obtained stakeholders’ expectations B 管理相关方参与程度 Managed stakeholder engagement C 完成相关方登记册 Completed the stakeholder register D 定义每个相关方的角色与职责 Defined roles and responsibilities for each stakeholder