在公司重组之后,一位团队成员现在向不同的职能经理报告。项目经理应该更新哪份文件以反映这种新的报告结构?Following a company reorganization.a team member now reports to a different functional manager. What document should the project manager update to reflect this new reporting structure?
发布于 2021-04-19 22:43:00
【单选题】 A 相关方参与计划 Stakeholder engagement plan B 资源日历 Resource calendar C 项目团队任务分配 Project team assignments D 资源管理计划 Resource management plan