【单选题】
A 遵从分配调到新项目 Move to the new project according to assignment.
B 召开实施后评审会议 Conduct a post-implementation review meeting.
C 与新团队分享之前项目的经验教训 Share the lessons learned from the previous project with the new team.
D 要求项目管理办公室(PMO)和过程经理收集经验教训 Ask the project management office(PMO)and the process manager to collect the lessons learn