项目经理正在编写采购工作说明书(SOW),以分包新工厂的机器安装任务。项目经理应该查阅哪一份文件来确保其与项目目标一致?A project manager is writing this procurement statement of work(SOW)to subcontract a new plant's machinery installation, Which document should the project manager refer to ensure it is consistent with the project objectives?
发布于 2021-04-19 22:43:14
【单选题】 A 供方选择标准 Source selection criteria B 项目章程 Project charter. C 采购文件 Procurement documents. D 项目管理计划 Project management plan.