在项目执行期间,客户请求对可交付成果进行一个小变更,客户表示该变更不会产生财务影响,项目经理应该怎么做?During project execution, the customer requests a minor change to a deliverable. The customer advises that the change will have no financial impact. What should the project manager do?
发布于 2021-04-19 22:43:13
【单选题】 A 指示项目团队进行变更 Instruct the project team to make the changes B 要求客户提交一份正式的变更请求 Ask the customer to submit a formal change request C 制定估算依据 (BOE)Develop a basis of estimate (BOE) D 更新问题日志 Update the issue log