【单选题】
A 在风险登记册中记录异议,并请求批准转移可交付成果 Record objections in the risk register and request approval to transfer deliverables
B 使用渐进明细更新项目范围,并让相关方批准可交付成果 Use progressive detail to update project scope and get stakeholders to approve deliverables
C 请求举行包括相关方和其他项目团队成员的会议,以评估相关方的顾虑 Request a meeting involving interested parties and other project team members to assess their concerns
D 停止可交付成果转移过程,并与项目指导委员会一起修订项目进度计划,修订时应考虑转移迟延的情况 Stop the deliverable transfer process and work with the Project Steering Committee to revise the project schedule to take account of transfer delays