在一次检查中,生产阶段被停止,因为检查员声称缺少监管标签。项目经理应该怎么做?During one inspection, the production phase was stopped because the inspector claimed a regulatory label was missing. What should a project manager do?
发布于 2021-04-24 23:10:04
【单选题】 A 审查风险管理计划。 Review the risk management plan. B 更新经验教训的登记。 Update the registration of lessons learned. C 审查质量管理计划。 Review the quality management plan. D 进行专家判断评估。 Perform expert judgment assessments.