【单选题】
A 让该相关方遵循变更控制过程使其请求获批 Have the interested party follow the change control process to have their request approved
B 接洽项目发起人,了解该变更能否列入预算和范围 Contact the project sponsor to see if the change can be included in the budget and scope
C 动用应急预算将该变更纳入项目范围 Use the emergency budget to include the change in the project scope
D 将相关方的请求上报给项目发起人,以确认是否需要实施该变更 The request from the interested party is reported to the project sponsor to confirm whether the change needs to be implemented