作为中型适应型软件开发项目的项目经理,您正在使用一个工具来确定当前迭代中有多少工作需要完成。 这里提到了什么工具?As a Project Manager of a mid-sized adaptive software development project, you are using a tool to determine how much work is remaining to be done in the current iteration. What tool has been referred over here?
发布于 2021-04-24 23:10:44
【单选题】 A 燃尽图 Burndown Chart. B 燃起图 Burnup Chart. C Why-why 图 Why-why Diagram. D 运行图表 Run Chart.