审查问题日志的团队意识到一项关键可交付成果可能会延期,这将影响项目进度计划几个月时间。该项目在公司的投资组合中具有更高的优先级。 项目经理应该做什么?A team reviewing the issue log realizes that a key deliverable may delayed,which will impact the project schedule by a few months.This project has high priority within the company's portfolio What should the project manager do?
发布于 2021-04-24 18:10:55
【单选题】 A 在问题日志中描述其影响 Describe the impact in the issue log B 更新项目的进度基准 Update the project's schedule baseline C 请求项目发起人的支持 Ask the project sponsor for support D 在风险登记册中添加一个新的高概率风险 Add a new,high-probability risk to register