在项目开始时,一位相关方通知项目经理他们将缺席多次项目会议,项目经理首先应该做什么?At the beginning of the project, a related party informs the project manager that they will be absent from multiple project meetings. What should the project manager do first?

发布于 2021-04-24 18:10:45
【单选题】
A 识别一位替代相关方在该相关方缺席时参加会议 Identify an alternate party to the meeting in the absence of that party.
B 通过映射他们的权力和影响力来分析相关方 ana-lyze interested parties by mapping their power and influence.
C 监控该相关方,并在会议之前请求提供信息 Monitor the interested party and request information before the meeting
D 坚持要求让该相关方参加所有会议以避免开创先例 Insist on having the relevant party participate in all meetings to avoid setting a precedent