项目已经执行六个月了,在与五名团队负责人中的两名讨论项目状态时,项目经理注意到一个信息差。 若要解决这个问题,项目经理应该查询哪一份计划?A project has been underway for the last six months. While discussing its status with two out of the five team leads, the project manager notices an information gap. What plan should the project manager reference to solve this ?
发布于 2021-04-19 22:42:48
【单选题】 A 相关方参与计划 Stakeholder engagement B 沟通管理计划 Communications management C 资源管理计划 Resource management D 风险管理计划 Risk management