项目经理在一个平衡矩阵式组织中管理一个中等优先级项目。现在,更高优先级的项目需要该项目的一些团队成员。 若要确定哪些资源对其项目可用,项目经理应该做什么?A project manager is leading a medium-priority project in a balanced matrix company.Some of this project`s team members are now required for higher-priority projects. What should the project manager do to determine what resources are available for their project?
发布于 2021-04-19 22:41:36
【单选题】 A 与每个资源核对,以了解他们的工作量 Check with each resource to undermine their workload B 审查资源管理计划 Review the resource management plan. C 询问项目管理办公室(PMO) Ask the project management office(PMO). D 与职能经理沟通 Communicate with the functional managers.