在项目的初始阶段,通过了一项新法规。这项法规有可能会影响到项目的进度和预算。开始规划阶段之前,项目经理应该做什么?During a project's initial phase,a new regulation is introduce The regulation has the potential to impact the project's schedule and the budget. What should the project manager do before beginning the planning stage?
发布于 2021-04-19 22:41:37
【单选题】 A 执行定性风险分析 Perform a qualitative risk ana-lysis. B 将该风险包含在项目章程中 Include the risk in the project charter. C 更新风险应对计划 Update the risk response plan. D 请求变更进度计划和预算 Request a change to schedule and budget.