项目经理确定项目的进度绩效指数(SPI)为1.2,成本绩效指数(CPI)为0.8。项目目前的状态是什么?A project manager determines that the a project's schedule performance index(SPI)is 1.2,and its cost performance index(CPI)is 0.8.What is the project a current status?
发布于 2021-04-19 22:42:35
【单选题】 A 落后于进度,但低于预算 Behind schedule and under budget. B 超前于进度,并低于预算 Ahead of schedule and under budget. C 落后于进度,并超出预算 Behind schedule and over budget. D 超前于进度,但超出预算 Ahead of schedule and over budget.