—位团队成员通知项目经理有一个问题可能会破坏项目。项目经理将该问题添加到问题日志中,并要求团队找到解决方案。 项目经理下一步应该怎么做?A team member notifies the project manager of an issue that has the potential of disrupting the project.The project manager adds the issue log,and the team to find a resolution. What should the project manager do next?
发布于 2021-04-19 22:43:10
【单选题】 A 更新风险登记册 Update the risk register. B 修订项目管理计划 Revise the project management plan. C 确定适当的风险应对 Identify the appropriate risk response. D 通知相关方 Inform the stakeholders.