在一个施工项目期间,由于大雨影响了混凝土的一致性,混凝土无法使用。这种可能性及其估算成本已在风险登记册中确定。项目经理应该如何提供额外成本的资金?During a construction project,concrete is unable to be used because heavy rain affected its consistency:This possibility and its estimated cost were already identified in the risk register. How should the project manager fund the additional costs?
发布于 2021-04-19 22:43:04
【单选题】 A 应用预算储备 Apply the budget reserve. B 向客户索取储备 Request reserves from the client. C 使用管理储备 Use the management reserve. D 评估应急储备 Access the contingency reserve.