一个涉及国家教育新标准的项目正在执行中,在确认准备好的教科书期间,团队成员发现某些书籍不符合事先定义的项目标准。项目经理应该参考下列哪一项来确认这个问题?A project involving new national standards for education was under way, and during confirmation of the prepared textbooks, team members found that some of the books did not conform to predefined project standards. Which of the following should the project manager refer to to identify the problem?

发布于 2021-04-19 22:43:11
【单选题】
A 范围基准和质量核对单 Scope baseline and quality checklist
B 进度基准和质量核对单 Schedule baseline and quality checklist
C 项目基准和质量核对单 Project baseline and quality checklist
D 范围基准和质量测量指标 Scope baseline and quality metrics

查看更多

关注者
0
被浏览
122
  • 体验AI问答!更聪明、超智能!
  • 一款基于GPT的超级AI助手,可以对话、创作、写文案!
1 个回答

撰写答案

请登录后再发布答案,点击登录

发布
问题