客户要求项目经理在60天内交付项目,而之前原本计划在90天内交付,没有可以并行执行的活动,请求的变更已经获得变更控制委员会(CCB)的批准。若要满足这项要求,项目经理应该做什么?A customer asked the project manager to deliver a project in 60 days that was previously scheduled for delivery in 90 days.No activities can be performed in parallel.The requested change is approved by the change control board(CCB).What should the project manager do to fulfill this request?
发布于 2021-04-19 22:41:49
【单选题】 A 为项目进度计划创建应急储备 Create a contingency reserve for the project schedule. B 对项目进度计划赶工 Crash the project schedule. C 在项目进度计划中创建项目阶段 Create phases in the project schedule. D 快速跟进项目进度计划 Fast track the project schedule.