一家公司准备重新启动一个暂停的项目。遗憾的是,整个项目团队均已解散。项目经理应该使用什么来重新制定项目计划?A company is ready to re-initiate a project that was put on hold Unfortunately, the entire project team was release What should the project manager use to replan the project?
发布于 2021-04-19 22:41:51
【单选题】 A 经验教训储存库 Lessons learned repository B 项目发起人的意见 Sponsors'input C 商业论证 Business case D 可行性研究 Feasibility study