项目发起人要求立即对具有明确任务的新项目进行估算。项目经理认为这个项目与另一个最近完成的项目类似。项目经理应该使用什么来确定估算?A project sponsor requests immediate estimates for a new project with well-defined tasks.The project manager determines that this project is similar to another recently completed project.What should the project manager use to determine the estimates?
发布于 2021-04-19 22:42:14
【单选题】 A 储备分析和成本汇总 Reserve ana-lysis and cost aggregation B 专家判断和成本估算 Expert judgment and cost estimating C 资金平衡和储备分析 Funding reconciliation and reserve ana-lysis D 类比估算和成本汇总 ana-logous estimating and cost aggregation